Mechanical Site-Acceptance Checklist for Rack, Wall-Mount and Cabinet ESS
The crate is at the dock or the plant-room door. The search most importers already know is “incoming inspection”: open-circuit voltage, documents, sometimes a capacity sample. LJY’s live LiFePO4 incoming inspection guide covers that electrical and document workflow. It does not tell a buyer how to accept a 19-inch rack module, a wall-mounted pack, or a floor or C&I cabinet against the approved mechanical drawing.
This page is the missing companion: a mechanical site-acceptance checklist for procurement and incoming-goods teams. It is a comparison of the delivered unit with a frozen drawing issue and the purchase contract. It is not a commissioning procedure, and it is not a construction or installation guide. Dimensions, mass and IP marks vary by model. Do not accept a unit against a typical-class website range, a cell drawing, or another manufacturer’s clearance.
LJY Energy is a China-based LiFePO4 battery supplier and OEM/ODM coordinator. The acceptance criteria that govern a given order are the ones written into that order.
1. Two inspections, two jobs
| Inspection | Typical question | Live LJY starting point | This page |
|---|---|---|---|
| Electrical / document incoming inspection | Do the documents, marks, voltage and agreed sample tests match the contract? | Incoming inspection guide | Not repeated here |
| Mechanical site acceptance against a drawing | Does this enclosure match the approved issue — size, holes, glands, lifting points, mass, accessories? | The drawing pack frozen in the pre-delivery drawings checklist | Yes |
Fact (tender practice): some public specifications already separate these ideas. The AEGCL battery-bank tender lists acceptance tests that include polarity marking, verification of dimensions, and ampere-hour capacity. The BHEL BESS package requires a site acceptance test and then as-built drawings if the field installation has changed the layout. Those documents are examples of buyer practice. They are not LJY’s own factory procedure, and they do not set your contract unless you have written them in.
Fact (live LJY incoming-inspection page): final acceptance criteria belong in the purchase contract. The same rule applies here. If your contract is silent on mechanical tolerances, stop and agree them against the drawing; do not invent a “±2 mm” rule on the warehouse floor.
If you never approved a drawing, mechanical SAT has no reference. Complete the drawings freeze and the site-fit RFQ first, preferably before production.
2. Hold points before you uncrate in a way you cannot reverse
- Photograph the packed unit, labels and any damage before breaking seals, as the electrical incoming-inspection guide already recommends for evidence.
- Read the packing list against the purchase order and against the approved drawing issue number (not an older email PDF).
- Confirm that the crate outline and packed mass, if they were stated on the approved pack, are consistent with what arrived. Packed values vary by model and packing method; there is no single LJY crate size on this page.
- Do not drill, cut, relabel, or energise a unit that is already in dispute. Quarantine is the incoming-inspection page’s rule for non-conforming product; use the same idea for a mechanical mismatch.
3. Compare the unit with the approved issue
Work with a tape, a scale if mass is a contract item, the approved PDF or paper drawing, and a camera. Record the drawing number, revision and the serial or batch on every photograph.
| # | Check | Pass looks like | Fail / hold |
|---|---|---|---|
| 1 | Identity | Model (or project code), serial, and drawing issue on the nameplate or packing marks match the approved issue and the purchase order | Wrong issue, missing serial, or a unit that only matches a superseded drawing |
| 2 | Overall outline | Measured width, depth and height, including handles, glands, hinges, wheels and lifting eyes, are within the tolerances written on the approved drawing or in the contract | A website typical-class range was used as the tolerance; or a protrusion that the drawing showed was omitted or moved |
| 3 | Mounting interface | Hole or slot coordinates, sizes and rail or bracket mating face match the approved sheet | Holes drilled to a “close enough” unofficial sketch |
| 4 | Cable entry | Gland plate side, height and hole count match the approved sheet | Glands on the opposite side to the approved issue |
| 5 | Doors, covers, display | Swing or removal direction matches the drawing; no transit damage that prevents the shown opening | Door that cannot open as drawn without hitting a packed accessory or a bent frame |
| 6 | Lifting and handling points | Eyes, fork pockets or indicated lift points are present as drawn | Missing eyes, or lift points added in the field without a revised drawing |
| 7 | Mass | If the contract requires a weighing, the reading is compared with the mass on the approved drawing or nameplate, using the method the contract names | Using a generic “100Ah packs weigh 12–14 kg” rule. That kind of rule on small 12V packs is not a rack- or cabinet-mass method and is not used here |
| 8 | Ingress mark | If an IP code was a contract item, the mark on the unit matches the approved drawing and the purchase order | An IP word on a brochure, or a different code from the one confirmed for the build |
| 9 | Accessories in scope | Rails, wall bracket, keys, feet, casters, busbars or cables listed on the drawing or BOM are present and undamaged | Bracket missing, or a different bracket from the approved interface |
| 10 | No unauthorised modification | No extra holes, cut glands, or relabelled nameplates | Any field modification not covered by a revised, approved issue |
Tolerances. Use only those printed on the approved drawing or written in the contract. If neither document states a tolerance, record the measurement and raise a written question. Do not adopt another project’s millimetre band.
IP codes. IEC 60529 defines what an IP code means as a test classification (for example IP20, IP54, IP65). Mechanical SAT checks that the marked code, if required, matches the approved issue. It does not itself re-test the enclosure to IEC 60529 unless the contract says so.
4. Form-factor notes at the dock
- 19-inch rack modules. “It is 3U” is not a complete inspection. Confirm the outline, including rear or side protrusions, against the approved module drawing. IEC 60297-3-100:2008 explains the 482.6 mm / 1U = 44.45 mm system; it does not replace the module drawing. The live 51.2V rack-mount page publishes only a typical-class size and mass band; do not use that band as an acceptance tolerance.
- Wall-mounted packs. Check the bracket or backplate against the approved interface, and check that indoor and outdoor enclosures were not swapped. The outdoor IP65-class page states that dimensions, weight, bracket and IP rating are confirmed per project.
- Floor-standing cabinets. The live 314Ah cabinet page says exact dimensions are confirmed in the quotation drawing and uses an approximate “≈100+ kg” handling remark. Acceptance weighing, if required, uses the approved drawing or nameplate, not that remark.
- C&I outdoor cabinets. The live 100kW / 215kWh-class page states that dimensions, weight and foundation are confirmed in drawings and describes a multi-tonne class. Unloading and placement are the buyer’s qualified contractor’s work. This checklist only asks whether the delivered enclosure matches the approved issue before anyone cuts a pad or a trench to a wrong outline.
5. What not to do
- Do not “make it fit” by cutting the building, relocating glands, or drilling new mounting holes unless a revised drawing and a written contract change are approved first.
- Do not treat another brand’s installation distances as a default. (A worked example, clearly labelled: Pylontech’s US2000C manual states 440 × 410 × 89 mm, 22.5 kg, and siting distances of more than 2 meters from a heat source and more than 0.5 meters from an inverter air outlet — for that model only.)
- Do not turn this checklist into an electrical test plan. Voltage, IR, capacity and BMS checks stay on the incoming-inspection guide.
- Do not claim or assume a certificate, IP rating, or fire-separation distance that is not on the approved issue and the contract.
6. Non-conformance, claims, and later as-built drawings
The incoming-inspection guide already describes a practical claims path: quarantine, photograph, notify the supplier in writing, and refer to the contract. Use the same path for a mechanical mismatch, and attach the approved drawing issue next to the photograph of the unit.
If, after a written agreement, the installed layout differs from the approved issue, some purchasers require an as-built drawing (the BHEL BESS package is one public example). An as-built is a later record. It is not a way to accept, after the fact, a unit that never matched the issue you approved for production.
Factory acceptance tests, if they were contracted, do not automatically cancel a site mechanical check. Confirm in the order whether FAT records are available and which checks are repeated on site.
7. Related LJY pages
- Pre-delivery mechanical drawings checklist
- Installation conditions RFQ checklist
- LiFePO4 incoming inspection guide
- Rack-mount ESS selection guide
- 51.2V rack-mount, 48V 200Ah rack-mount, 314Ah floor cabinet, C&I 100kW/215kWh-class cabinet, outdoor IP65-class wall-mount
FAQ
Can I accept the cabinet against the millimetre range on the website?
No. Accept against the approved drawing issue and the contract. Website ranges, where they exist, are typical-class orientation and are stated as confirmed per project.
The electrical incoming-inspection page mentions a 12–14 kg check for a 100Ah battery. Can I use that on a rack or cabinet?
No. That remark belongs to a different incoming-inspection context for small packs. Rack modules and cabinets have model-specific masses on their own drawings and nameplates.
What if the drawing has no tolerance?
Record the measurement and raise it in writing. Do not invent a tolerance at the dock.
Do I need to re-test IP65 with a water jet on site?
Only if the contract says so. The default mechanical check is that the marked code matches the approved issue. IEC 60529 testing is a laboratory method, not a warehouse improvisation.
If you want the mechanical acceptance points written into an order, send the approved drawing issue and this checklist through the contact form. Use the existing inquiry code ESS-Storage-RFQ and state in the message that this is a mechanical site-acceptance request against an approved drawing.