Pre-Delivery Mechanical Drawings Checklist for Rack, Wall-Mount and Cabinet ESS
An EPC has already poured a pad, or a distributor has already reserved a plant-room bay, using a brochure photograph and a typical “51.2V cabinet” table. The unit that later arrives is deeper than the door swing, the cable glands are on the opposite side, or the lifting eyes do not match the site crane plan. The search that usually follows is not “how do I install a battery.” It is: what mechanical drawings should I request and freeze before an ESS ships?
This page is a procurement checklist for buyers of 19-inch rack modules, wall-mounted packs, floor-standing cabinets and outdoor C&I cabinets. It explains which drawings to put in the RFQ, how to approve a revision, and how to compare that frozen issue with site measurements. It is not a construction or installation manual. It does not give a single LJY dimension, weight, IP rating or safety distance, because those values vary by model and are confirmed on the project drawing and the formal quotation.
LJY Energy is a China-based LiFePO4 battery supplier and OEM/ODM coordinator. Enclosure details, documents and commercial terms are confirmed per project. They are not assumed from a marketing photograph.
1. Freeze the drawing before production, not after the crate arrives
Fact (tender practice): public battery and BESS specifications routinely require outline or general-arrangement drawings with dimensions before the purchaser can judge whether the equipment will fit, and they require those drawings to be approved. Examples include the AEGCL battery-bank tender (outline drawings “showing sufficient details to enable the purchaser to determine whether the design proposed can be installed satisfactorily”) and the BHEL BESS package (OGA / layout drawings with dimensions, then site acceptance, then as-built drawings). The Lewes Board of Public Works BESS draft likewise requires approval drawings that state arrangement, size and pertinent dimensions, with an owner/engineer review cycle.
Inference (procurement practice, not a law): if the only “drawing” you have is a rendered product photo or a typical-class range on a website, you do not yet have a production freeze. Website ranges exist to orient a class of product. They are the wrong document to give a civil or rack designer.
What this means for an RFQ
- Name the form factor you actually want: 19-inch rack module, indoor wall-mount, outdoor wall-mount, floor-standing cabinet, or C&I outdoor cabinet. Do not write only “ESS battery.”
- Ask for a mechanical drawing pack for the exact configuration (capacity class, enclosure option, gland side, breaker position, casters or feet, wall bracket, colour/logo if they change hole locations).
- State that manufacturing should not start — and that a later silent revision is not acceptable — until a named drawing issue is marked approved for production.
- Keep the approved issue number on the purchase order, the packing list request, and the later site-acceptance checklist.
Related live LJY pages already point in this direction, without being a drawings checklist: the 51.2V 314Ah floor-standing cabinet tells buyers to ask for the current drawing in the RFQ and not to use third-party 314Ah cell dimensions as cabinet L×W×H; the 100kW / 215kWh-class C&I cabinet states that dimensions, weight and foundation are confirmed in drawings.
2. Drawing pack to request (use as an RFQ attachment)
Ask the supplier to say, item by item, whether the file will exist for your configuration, in which format (PDF is the usual review copy; a CAD file if your contract requires it), and on which revision. If an item is not applicable — for example, a wall bracket on a 19-inch module — have them mark it “N/A” rather than leaving a gap.
| # | File or sheet | What the buyer should be able to check | Notes |
|---|---|---|---|
| 1 | Cover / revision block | Drawing number, revision, date, model or project code, approval status | The later site inspection compares the nameplate and the crate to this issue, not to an earlier email attachment. |
| 2 | Outline / general arrangement (GA / OGA), three views | Overall width, depth, height, including handles, hinges, glands, wheels, lifting eyes and any rear or side protrusion | “19-inch” or “3U/4U” is not a complete outline. Depth and protrusions vary by model. |
| 3 | Dimensioned mounting interface | Hole coordinates, hole size, slot direction, rail or bracket mating face | For racks, this is the ear / cage-nut pattern. For wall units, the bracket interface. For cabinets, feet, anchor points or pad fixing. |
| 4 | Mass and centre of gravity | Net mass, if known separately from packed mass; CG position if lifting or wall mounting is planned | Mass varies by model and options. Do not substitute a generic pack-weight rule of thumb. |
| 5 | Lifting, forklift and handling points | Eye locations, fork-pocket size and side, any “do not lift here” note that appears on the drawing | The drawing is the procurement reference. Site lifting method is the buyer’s qualified contractor’s decision. |
| 6 | Cable entry and gland plate | Side, height, hole count, gland type or plate size, reserved space for the buyer’s cable bend | Left-hand vs right-hand entry is a common cause of rework. |
| 7 | Door, cover and display swing | Opening angle or clearance needed in front or at the side, as dimensioned on the drawing | If the drawing is silent, ask for the dimension before you approve. Do not invent a millimetre figure. |
| 8 | Terminal, breaker and earthing locations | Front vs rear access, protective cover, earthing stud | Needed for cabinet and wall layouts as well as rack front-terminal plans. |
| 9 | Nameplate and marking locations | Where the model, serial, mass and ingress marking will be placed | Acceptance later checks that the marks match the purchase order and the approved issue. |
| 10 | Ingress-protection statement as it will be marked, if an IP code is specified | The code (for example IP20, IP54, IP65) and the enclosure or build it applies to | An IP code is defined by IEC 60529 test methods. It is only a claim if the supplied build is rated and marked. LJY product pages treat IP as confirmed per project, not as a default. |
| 11 | Packed / crate outline and packed mass | Length, width, height of the transport pack; packed mass | Used to check doors, lifts and aisles before shipment, together with the site-fit RFQ. |
| 12 | Accessory list on the drawing or a linked BOM | Rails, wall bracket, keys, feet, casters, busbars, communication cables that are in scope | Acceptance later checks that the crate matches this list. |
Fact vs inference. Rows 1–12 are a procurement pack assembled from common tender practice (outline / OGA drawings, dimension verification, approval reviews) and from the mechanical questions already raised on LJY product pages. They are not a claim that every LJY quotation automatically includes every sheet. Which files exist for a named model and destination are confirmed in writing with the quotation.
3. Form factor: what “19-inch,” “wall-mount” and “cabinet” do and do not fix
19-inch rack modules
Fact (IEC 60297-3-100:2008): the standard is titled for mechanical structures of the 482.6 mm (19 in) series. The front-panel height increment 1U equals 44.45 mm. The same table lists the 3U envelope as 133.35 mm and the 4U envelope as 177.80 mm (front-panel H1 values in that table are 132.55 mm and 177.00 mm). This is a rack-interface standard. It does not fix battery module depth, heat-exhaust direction, cable-exit side, or mass.
The live 51.2V rack-mount LiFePO4 page describes a 19-inch, 3U (100Ah class) / 4U (200Ah class) form factor and currently publishes a typical-class size band of approximately 442–483 × 460–540 × 136–175 mm and a typical-class mass band of approximately 43–50 kg, with IP20 listed as an indoor-rack typical value. The same page states that final specifications, including enclosure details, are confirmed per project in the formal quotation. Do not treat that band as a frozen LJY model drawing. Put the approved outline on the order.
When you already have a cabinet, photograph or measure usable U height, rail depth, residual rail load (from the cabinet maker, not guessed), and the planned cable-exit side, then send those constraints with the RFQ. The rack-mount ESS selection guide already asks for cabinet depth, U-height and cable exit; this drawings checklist is the document step that follows.
Wall-mounted packs
A wall unit is not a 19-inch rail product. The drawing must show the bracket or backplate, hole pattern, and the mass that the wall structure will have to carry. The live outdoor IP65-class wall-mounted page states that dimensions, weight and bracket are confirmed per enclosure design, and that the IP rating of the build is confirmed per project. Indoor wall formats are listed separately (51.2V 100Ah, 51.2V 200Ah). Do not mix indoor and outdoor enclosure drawings.
Floor-standing and C&I cabinets
For the wheeled 51.2V 314Ah floor cabinet, the live page’s Size/fitment section says exact dimensions are to be confirmed in the quotation drawing, and it uses an approximate “≈100+ kg” handling remark — that remark is not a certified weighing and must not be copied onto a civil loading calculation. For the 100kW / 215kWh-class outdoor cabinet, the live page describes a multi-tonne class and says dimensions, weight, foundation, pad, trenching and maintenance clearance are confirmed in project drawings. In both cases the correct procurement action is: request the current drawing, approve it, and keep that issue.
4. How to compare a drawing with the site (procurement review, not installation)
This step is a desk review by the buyer, the buyer’s designer, or a qualified contractor the buyer appoints. It is not a set of installation instructions.
- Record site constraints in writing: door and corridor widths and heights, lift or stair limits, plant-room or pad outline, ceiling or beam height, existing rack U and depth, wall type (to be assessed by someone competent for load-bearing), and any local permit document list you already know.
- Compare those measurements with the overall outline and the packed crate outline on the approved drawing. A unit that fits on the pad can still fail at the loading dock.
- Check service and door-swing dimensions only as they appear on the supplier’s approved drawing. If a figure is missing, ask for it. Do not fill the gap with a “usual” millimetre or metre value, and do not treat another manufacturer’s clearance as a default (see the companion installation-conditions RFQ checklist).
- Floor load and wall load are structural questions. The drawing supplies mass and, if provided, centre of gravity. Whether the floor or wall is adequate is confirmed by the buyer’s competent person, not by a website article.
- Mark conflicts as comments on the drawing issue. Do not “approve with a verbal workaround” (cutting a door frame, moving glands on site, or drilling new holes) unless a revised, re-approved drawing and a written contract change say so.
Fire-separation and permit distances, where they apply, are set by the destination authority having jurisdiction and by the manufacturer’s approved instructions for the listed or contracted product. They are not a single LJY figure and are not restated as a universal number on this page.
5. Approval status words that should appear in the order
Inference (document-control practice): buyers avoid later disputes when the purchase documents use the same revision language as the drawing block. A workable set is:
- For review — not for production.
- Approved for production — the issue that may be built and shipped, with the date and the approver’s name or company.
- Superseded — an older issue that must not be used at incoming inspection.
- As-built — only after any agreed field change; that is a later document, not a substitute for the pre-delivery freeze.
Ask the supplier to notify you in writing before any change to an approved issue, and to stop shipment if the unit no longer matches that issue.
6. RFQ skeleton
Copy and complete:
Company / role / country / destination site:
Form factor (19-inch rack / indoor wall / outdoor wall / floor cabinet / C&I cabinet):
Capacity or energy class requested (for example 51.2V 100Ah, 200Ah or 314Ah class, or 100kW/215kWh class):
Inverter or PCS brand, model and firmware (if known):
Indoor or outdoor; any IP code you want stated on the nameplate (to be confirmed, not assumed):
Site limits attached (door, lift, U-height, rail depth, wall type, pad outline, packed-size limit):
Drawing pack requested: items 1–12 in the LJY pre-delivery mechanical drawings checklist, or a marked N/A:
Approval cycle (who reviews, how many working days, language of the title block):
Required file formats (PDF review copy; CAD if the contract requires it):
Inquiry code: ESS-Storage-RFQ (existing form code; state in the message that this is a pre-delivery mechanical drawing-pack request)
Send the completed list through the contact form. Use the existing inquiry code ESS-Storage-RFQ and state in the message that you are requesting a pre-delivery mechanical drawing pack. Commercial terms, document packs and the actual drawing issue are confirmed in the formal quotation. This page does not state MOQ, price, stock or lead time.
7. Related LJY pages
- Installation conditions RFQ checklist — what site data to collect before you ask for a drawing.
- Mechanical site-acceptance checklist — how to compare the arrived unit with the approved issue.
- Rack-mount ESS selection guide — form factor and voltage class.
- 51.2V rack-mount LiFePO4 battery, 48V 200Ah rack-mount, 51.2V 314Ah floor cabinet, C&I 100kW/215kWh-class cabinet, outdoor IP65-class wall-mounted battery.
- LiFePO4 incoming inspection guide — electrical and document checks; it does not replace a mechanical drawing comparison.
FAQ
Can I design the room from the typical millimetre range on the rack product page?
No. The live rack page publishes a typical-class band and says final enclosure details are confirmed in the formal quotation. Use the approved project drawing.
Are 314Ah cell drawings enough for a 16.08 kWh cabinet?
No. The live cabinet page already says not to use third-party 314Ah cell dimensions as cabinet L×W×H. Ask for the cabinet drawing.
Will LJY publish one official clearance for every rack, wall unit and cabinet?
No. Clearances, where they exist, belong on the approved drawing and in any destination-code review. They vary by model and by jurisdiction. This checklist does not invent a unified safety distance.
Does an IP code on a brochure freeze the enclosure?
No. IEC 60529 defines how an IP code is tested. Whether a supplied build carries a stated IP code is confirmed per project and should appear on the approved drawing and the nameplate plan.
When should I send the inquiry?
Once you can name the form factor, the destination, and at least the access or room limits you already know. Attach photos or a simple room sketch if you have them. Use inquiry code ESS-Storage-RFQ and mention the drawing pack in the message.