LiFePO4 Delivery Document Acceptance Checklist for Importers
The truck is at the gate, the seals are still intact, and somebody has to sign for an imported LiFePO4 shipment. Most receiving procedures jump straight to voltage or capacity tests. Those tests matter, and they are already covered in the incoming inspection guide. What is usually thinner is the document file: whether the cargo you are about to accept is the same cargo described on the invoice, the packing list, the transport papers, and the UN38.3 test summary you were given before the vessel or aircraft moved.
This page is a delivery-document acceptance checklist for importers, distributors, and warehouse teams. It is not a customs ruling, not a claims-law primer, and not a substitute for the acceptance criteria you should have written into the purchase contract before you paid.
Short answer
- Close the paper file before you break down pallets for electrical testing.
- Match identifiers across the commercial invoice, packing list, bill of lading or air waybill, UN38.3 test summary, SDS (if one was issued), and the marks and labels on the actual packages.
- Photograph the sealed load, the marks, and the documents together. Record batch or serial numbers as they appear on the cargo.
- If identifiers do not match, or piece counts and weights do not match, quarantine the discrepancy and notify the supplier in writing. Do not invent a claims deadline on this page; use the period and process you already agreed in the order.
- Physical tests (voltage, internal resistance, capacity, BMS checks) come after the document and identity checks, using the incoming inspection guide.
What should already be in the file before arrival
The cheapest time to find a document problem is before booking, not at the dock. The pre-shipment pack is described in the lithium import guide, the sea-freight IMDG pack, and the air-freight IATA pack. At delivery you are not creating those documents; you are checking that the arrived cargo still matches them.
Bring to the dock, on paper or as a single digital folder:
- Purchase order or confirmed quotation
- Commercial invoice
- Packing list
- Bill of lading, sea waybill, or air waybill (and house/master references if both exist)
- UN38.3 test summary for the exact type, and the unique report number (how to read the summary)
- SDS, if one was issued (SDS guide)
- Any agreed certificates or inspection records named in the order
- Photographs of packaging and marks taken at origin, if the supplier provided them
- The written acceptance criteria from the contract (quantity tolerance, document list, what happens if a model or batch does not match)
Dock-side matching table
Check these fields across documents and against the packages. Mark each row pass, fail, or not applicable. A blank row is not a pass.
| Field | Invoice | Packing list | B/L or AWB | UN38.3 test summary | SDS | Package / cargo |
|---|---|---|---|---|---|---|
| Proper product description (lithium-ion / LiFePO4, not a vague “batteries”) | □ | □ | □ | Lithium-ion vs lithium-metal vs sodium-ion | Transport section, if present | Marks and UN number, if required for the mode |
| Exact model / SKU | □ | □ | if shown | Model numbers on the summary | Product identifier | Nameplate, carton mark, or label |
| Watt-hour rating (and voltage / capacity if shown) | □ | □ | if shown | Wh or lithium-content field | if shown | Case Wh mark, if used |
| Quantity and package count | □ | □ | □ | n/a | n/a | Counted pieces and pallets |
| Net / gross weight | □ | □ | □ | Mass on the summary is design-type mass, not the shipment total | if shown | Scale check if you use one |
| Manufacturer or shipper name | □ | □ | □ | Manufacturer contact block | Supplier / manufacturer block | If marked |
| Unique test-report number and date | if referenced | if referenced | n/a | Must be present | n/a | Keep a copy in the receiving file |
| Batch / serial / production date | if agreed | □ | n/a | n/a (design type, not a lot certificate) | n/a | As marked on cells, packs, or cartons |
| UN number and packing instruction (as booked) | if shown | if shown | if shown | n/a | transport section, if present | Labels and marks on the outer packaging |
| Seal / container / package condition | n/a | n/a | seal numbers if FCL | n/a | n/a | Photograph seals and damage before unpacking |
Fact vs inference. The UN38.3 summary identifies a design type. It will not usually list your shipment’s batch numbers. Inference: some buyers treat a test summary as a lot-release certificate. It is not. Batch identity has to come from the packing list and the marks on the goods.
The mass on the test summary is the mass of the tested type, not the total weight of the container. Do not “fail” a summary because it does not equal the bill of lading weight.
Sequence that keeps the evidence usable
- Photograph the sealed arrival — container doors or trailer, seal numbers, pallet count, and any visible damage, before breaking seals.
- Compare seal and package counts with the bill of lading or air waybill and the packing list.
- Photograph outer marks and labels (UN number, Class 9 or lithium-battery mark, cargo-aircraft-only mark if it was an air shipment, handling marks) so you can compare them with the booked mode later.
- Run the matching table above and write down every mismatch, including spelling variants of the model name.
- Record batch and serial numbers as found, alongside the packing list.
- Only then move accepted goods into the inspection area for the physical tests in the incoming inspection guide.
- File the photographs, the completed checklist, and the document pack together. Keep them for as long as your quality system and the contract require. This page does not invent a retention period.
When the papers and the cargo disagree
Typical mismatches, and a practical response:
- Model or Wh on the cargo or packing list does not match the UN38.3 summary. Quarantine the lot. Do not book onward transport, and do not treat the existing summary as covering a different type. Ask for a summary that identifies the arrived model, or for a written explanation of the identifier change.
- Piece count or weight disagrees. Recount, reweigh if you can, and notify the supplier and the forwarder in writing with photographs and the packing list. Do not sign an unqualified clean receipt if you have not been able to check counts.
- SDS or invoice chemistry / UN number disagrees with the marks. Stop and clarify before you store or reship the goods. An SDS transport section that says UN 3481 while the packages are marked and were booked as UN 3480 is a file problem, not a typo to ignore.
- Missing test summary at delivery. Recall whether it was already made available (website, earlier email, QR code). If it was never provided, request it now and record the gap. IATA does not treat a paper copy as mandatory with every shipment unless a State or operator requires it, but you still need the file to confirm the type you accepted.
- Damage or broken seals. Photograph first, then notify the carrier and supplier under the process in the contract and the transport document. This page does not state a protest deadline.
Do not invent legal conclusions here. Who pays for inspection, return, or replacement depends on the contract, the Incoterm, and the facts. Agree those rules in writing before payment. The incoming-inspection guide covers the later step of quarantining units that fail electrical tests.
Misconceptions
- “If the carton count is right, the documents are right.” Counts can match while the model, Wh, or batch does not.
- “Signing the delivery note only confirms that pallets arrived.” In practice, an unqualified signature is often treated as acceptance of the stated goods. If you could not complete the check, record what was and was not verified.
- “The UN38.3 file is a batch certificate.” It is a design-type test summary. Batch traceability is a different record.
- “Customs clearance already proved the documents.” Import clearance and buyer acceptance are different jobs. HS classification is still the importer’s responsibility; see the HS code guide.
- “We can fix a model mismatch after we sell the stock.” If you resell, your own buyers will ask for the same identifiers. The import guide section on documents your buyers will ask for is the planning step; this checklist is the receiving step.
What this page does not decide
- It does not set a numerical voltage window, capacity tolerance, or sampling plan. Those belong in your contract and in the physical inspection guide.
- It does not state LJY Energy’s warranty period, MOQ, price, or claim window. Warranty terms, when they apply, are in the quotation and the importer warranty guide.
- It does not tell you which destination permits, conformity assessments, or producer-responsibility filings apply in your country.
Where LJY fits
When you request a quotation, ask for the receiving-document list for the named models: invoice and packing-list fields, UN38.3 test summary, SDS if issued, and any other documents that will be supplied for that order. Use the contact form. Which documents exist for a given model is stated in the quotation; this page does not promise a fixed certificate set.
FAQ
Should I open cartons before I check the documents? Photograph seals and outer marks first, complete the matching table, then open cartons as needed to read batch or serial numbers and to start physical inspection.
What if the test summary was only provided as a link? That can still meet the “make available” duty for transport. For acceptance, download and file the document, and check that the identifiers match the arrived goods.
Do I need the full UN38.3 laboratory report at the dock? Not always. You do need a test summary that identifies the type. Request the full report if the summary is incomplete or conflicts with other papers.
Where do electrical tests fit? After identity and document checks, follow the incoming inspection guide.
Sources
- IATA, Lithium Battery Guidance Document, revised for the 2026 Regulations: test summary must be made available and is not automatically required as a paper copy with every shipment; an SDS is not a transport document. PDF. Accessed 17 November 2026. Guidance only.
- UNECE, UN Manual of Tests and Criteria, 8th revised edition and Amendment 1 (2025), sub-section 38.3. Publication page.
- On this site, the receiving electrical procedure remains the incoming inspection guide. This article adds the document-matching layer that that guide only states in brief.
Related guides
- Incoming inspection guide (physical tests)
- How to read a UN38.3 test summary
- LiFePO4 battery SDS guide
- Air freight IATA document pack
- Sea freight IMDG document pack
- How to import lithium batteries from China
- HS code classification guide
- Warranty terms for importers