In Hamilton, offices, shops and guest properties lose refrigeration, IT and lights when a hurricane or a fault takes the grid down, and a generator is often run for every short cut. Anyone searching for a LiFePO4 backup battery in Bermuda needs the bank in kWh from the measured essential watts × the outage hours, not from an ampere-hour label or a generator’s kVA. On a 120/240 V supply the inverter model and its battery voltage are confirmed before the bank is sized.
LJY Energy is a LiFePO4 supplier and OEM/ODM coordinator in Shenzhen; we are not a factory and we do not install. We coordinate 12.8V, 25.6V and 51.2V banks. The installer confirms the inverter, the mounting and the storm preparation on site.

Request a Hamilton backup sizing · WhatsApp +86 159 8945 0735
Example: essential loads of a small shop
| Load | Measured watts (example) | Hours on battery |
|---|---|---|
| Network, PCs and phones | about 300 W | 6 h |
| Fridge (cycling) | about 150 W average | 6 h |
| Lights | about 150 W | 6 h |
| Total | about 1.8 + 0.9 + 0.9 ≈ 3.6 kWh | plus losses and a reserve |
Example only. Measure the essential watts on site; a generator’s kVA or an inverter’s kW is not the energy the bank must store.
What the operator sends before a proposal
- Measured watts of the essential loads, not nameplates.
- Typical and longest outage hours.
- System voltage and the inverter model (120/240 V 60 Hz).
- Whether a genset stays as long-outage backup.
- Where the bank is mounted and how the site is prepared for storms.
Size one site, then repeat it
Chains and installers who size one Hamilton site from measured watts and then repeat the same bank avoid oversizing every shop. Prices and lead times only in a quotation.

Request a backup sizing
Send the measured essential loads and outage hours. We reply with a kWh-based bank proposal for batteries only.
LJY Energy, Jack Lai. Unit 705, Building 1, Lecai Industrial Park, 10 Kaijing Road, Longtian Street, Pingshan District, Shenzhen 518122, China. +86 159 8945 0735.